Timeline

January 2018: Planning permission granted

March 2018: Main contractor added to the project team

April to June 2018: Asbestos removal work begins

May 2018: Eden Mill vacate current location and move to new premises

June to August 2018: Demolition works commence, including building 33 (the blue building), canopies and roof coverings

August 2018 to February 2020: Construction works across all buildings

February 2020: Works complete and ready for relocation of colleagues

February/March 2020: Staff relocation begins